Exterior Renovation
Repair work on the exterior of the depot began the spring after the depot was moved.

Interior Renovation
Renovation and repurposing of the depot’s interior began the summer after the depot was moved.

Sculpture Garden
Planning for the garden began the fall after the depot was moved; physical work is currently underway.

Foundation
Building the new foundation and basement began immediately after the depot was moved to its new home.

Depot Move
The depot was successfully moved from its original location to its new home across the street on the Q-block on January 6, 2016

Move Preparation
Work to prepare for the depot’s move began in 2015, both on the structure of the depot itself and on the new site.